Regarding Production Order Confirmation
Production order confirmation
with future date is not allowed
Future dates can be configured in the confirmation configuration.
In configuration OPK4,
define confirmation parameters.
When this configuration comes up, in the "Checks"
Sections, the last parameter says
"Date in the future."
Check this box if you want your dates in the future.
It determines whether dates in the future can be used
in a confirmation.
If the indicator is not set, you cannot make any confirmations
using dates in the future.
If you try to do so, the system will issues an error message.
What is the importance of Production Order confirmation?
Is there any specification to use type of confirmation ie., CO11 or CO15
or CO11N ?
A confirmation documents the processing status of orders,
operations, suboperations and individual capacities.
You can enter a confirmation
- For an Opeartion (co11/co11n)
You have the following options:
- To confirm quantities, durations, activities or personnel
data.
- To make a confirmation at a particular point in time
(for example, at the start of setup or the finish of processing) enter
a
confirmation.
- When you confirm time events, the system calculates
the required duration. For example, the setup duration is the time between
setup start and setup finish.
- For an Order : CO15
If you enter a confirmation at order header level, the
system confirms all the operations that have a control key in which
confirmation is optional or necessary. The quantitiesconfirmed
in the operations are proportional to the quantities confirmed in the order
header.
*-- Rajesh
I want to stop the confirmation of production order
whenever there is no goods issue to the production order so that I can
get the correct material accounting report. I can't set backfliush
indicator to the material at Routing level because we are handling the
raw material in batches, so I have to assign the batches to
issue the raw material.( tcode CO27 ).
We have set the criteria to release the production
order is only availability of raw material in plant, so system checks only
the availability of raw material & releases the order.
Is it possible after issuing the raw material the release of order took
place?
Goods issues before release of order is not possible in
SAP.
You can think of following things.
1) In opj4,you can block release of order if it has missing
parts.
2) By using 'user exit' it is possible to disallow confirmation
if goods issues are not posted against each component.
*-- Shailendra
SAP PP Books
SAP Production
Planning and Control Certification, Interview Questions and Configuration
Reference Books
SAP PP Tips
SAP PP Tips and Production
Planning/Control
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|