My client is using strategy 50 MTO. There is a sale
order for 100 qty. Run MD50 and generated planned order for some
material (HALB). My client require that during planning, it need the system
to generate split planned order for each material by dividing the sale
order qty (i.e.) each planned order 20 qty.
Client require this material to create five planned order irrespective of sale order quantity, planned order qty should be always 100/5. --- You can define a production version for the material and in that version specify a distribution function which distributes the requirement in 20% splits. Distribution functions are defined in customizing under: Production -> Basic Data -> Bill Of Material -> Item Data
-> Item Data from Related Application Areas
If you want to split the planned order by percentage, you can use quota arrangement (MEQ1). Alternatively, you can distribute requirement quantity by defining a lot sizing procedure with the time in OMI4. However this type of splitting requires specifying min, max or static lot sizes in material masters. If you want to split order by capacity, then you might want to use fixed lot size, and finite capacity with option “changing production version on error”. |
|
See also