1) When you create a routing, you can assign it to a group. You combine routings in a group that describe:

A. Similar production processes for different materials
B. Different production processes for the same material
 

2) You can link routings and the material to be produced in the following ways:

A. A routing can be used to produce several materials
B. Material and routing can belong to different plants,
C. A material can be produced with different routings.
 

3) In the routing header you decide followings:

A. Whether you want to use inspection points
B. Which field combinations and therefore which reference you use to define the inspection points (for instance, container and shift)
C. Whether you want to combine product quantities for partial lots and batches
 

4) For each respective step in the operations for the routing you define,

A. What the inspection interval should be between the inspection points
B. How the quantity should be entered with time-related intervals
C. Whether the last partial lot assignment, which is therefore relevant to goods receipt, takes place during results recording
 

5) On the header level of a routing you define,

A. Whether the inspection scope is dynamically modified
B. On which level (lot or inspection characteristic) the dynamic modification takes place
C. Which dynamic modification rule is used when doing this
 

6) You can limit the selection of routing data by entering the following criteria:

A. Task list type
B. Material
C. Plant
D. Group
E. Group counter
 

7) You can print the following routing objects in addition to operations:

A. Long texts for routings or operations
B. Sub-operations with and without long texts
C. Material components
D. Production resources/tools with and without long texts
 

8) You can edit unlocked operations exactly like normal operations in a routing. In particular you can:

A. change the data of unlocked operations
B. insert other operations between unlocked operations
 

9) You have the following possible choices: You replace the reference operation set as followings:

A. in one particular routing
B. in all routing in which it is referenced
 

10) The following information is contained on the operation overview of the (rate) routing:

A. The group of the referenced reference operation set
B. The group counter of the referenced reference operation set
C. You can also call up the following additional information
D. The operation increment the system uses to insert operations from the reference operation set
E. Long text

---

Correct Answers

1) A, B

2) A, B, C

3) A, B, C

4) A, B, C

5) A, B, C

6) A, B, C, D

7) A, B, C, D

8) A, B

9) A, B

10) A, B, C, D

SAP PP Tips

See also
Display of all Routings for All Materials at a Time

Get help for your SAP PP Problems
SAP PP Forum - Do you have a SAP PP Question?

SAP Production Planning Books
SAP PP Certification, Interview Questions and Configuration Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.