General Conditions for a Project |
Question:Which of the following are examples of general conditions for a project?A. All documents generated out of the project structure
Correct Answer:B, C, and DExplanation (Option by Option):A. All documents generated out of the project structureIncorrectThese are deliverables or outputs of the project, not general conditions. They are created during the project lifecycle, whereas general conditions are predefined constraints or guiding elements present before or throughout execution. B. The time frame for executing the projectCorrectTime is one of the core pillars of project management. The schedule or duration of a project is a general condition, as it sets boundaries for planning, execution, and delivery milestones — especially critical in structured projects like SAP S/4HANA implementations. C. The objectives of the projectCorrectObjectives define the purpose and end goals of the project. Whether it's streamlining operations, automating workflows, or enhancing reporting — knowing what you’re aiming for is a key condition that drives all planning and resource decisions. D. Any financial and/or capacity-related restrictionsCorrectThese include budget limits, team capabilities, system infrastructure, and available skill sets. They directly impact what’s feasible within the project’s scope and must be identified early to avoid cost overruns or failed deliveries. E. Its network of activitiesIncorrectThis refers to the sequence of project tasks and dependencies — part of project planning, not foundational conditions. It defines how the work will be done, not what limits or governs the entire project. |
![]()
|
Read Also SAP PS Interview Questions SAP Project System Books
SAP Project System Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|