1) The BOM transfer function makes
it easier for you to assign material components in one or more BOMs to
network activities.
A. True
Which are the correct answers? --- 2) When you plan dates and resources in network activities, you have to manually determine the corresponding planned costs as a result of network costing. A. True
Which are the correct answers? --- 3) Results analysis is used to compare the planned and actual progress of your project with the results actually achieved. A. True
Which are the correct answers? --- 4) Which documents can be assigned to Network Orders? A. Assessment
Which are the correct answers? --- 5) What are the prerequisites for milestone billing of projects? A. Network activity and confirmation
Which are the correct answers? --- Answer 1) A 2) B 3) B 4) B, C and D 5) B and C
|
|