Project Structures

1) Activities are linked to each other by means of relationships. 
Choose the correct answer. 

a. True 
b. False 

Which are the correct answers?

---

2) A long text can be linked to more than one WBS element. 
Choose the correct answer. 

a. True 
b. False 

Which are the correct answers?

--- 

3) WBS elements cannot be further divided. 
Choose the correct answer. 

a. True 
b. False 

Which are the correct answers?

---

4) What are the basic elements that make up a network? 
There are two correct answers. 

a. Milestones 
b. Tasks 
c. Activities 
d. Relationships 

Which are the correct answers?

---

5) The various work packages in the project are described as individual ____________. 
Choose the correct answer. 

a. Project definitions 
b. Activities 
c. WBS elements 
d. Tasks 

Which are the correct answers?

---

Answer

1) a

2) b

3) b

4) c, d

5) c
 

SAP PS Tips

Read Also
SAP PS Interview Questions

SAP Project System Books
SAP PS Books - Certification, Interview Questions and Configuration

SAP Project System Tips
SAP PS Tips and Project System

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG.
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of
www.erpgreat.com or the content authors.