Q-1 You can maintain the planned costs for the general
costs activity (primary costs) in the following ways :
As the overall value for a cost element
Q-2 Material components for the activity are differentiated, by means of item categories, as follows : Stock material, item category L
Q-3 In SAP PS, Prices are calculated in one of the following ways : Using the strategy in the valuation variant
Q-4 With Distribution Key : If you have maintained distribution keys in both the activity
and the work center, the planned work is distributed to the periods per
the distribution key in the activity.
Q-5 You use Distribution Key : Overhead is calculated on the basis of the distribution
of planned work or costs by period.
Q-6 When you save the invoicing plan : The system automatically assigns it a unique number.
Q-7 You can use the asynchronous network costing to : Update the network costing
Q-8 If you want to use the network costing then Prerequisite is : The network must be activity assigned.
Q-9 IF you want to copy the project cost date , method may be : The system copies the plan data from the template to the
plan version.
Q-10 which types of values are recorded in the WBS element : Value of the quotation/sales order
Q-11 You can settle an order for a project, The case May be : Case 1: To the WBS element to which it is assigned
Q-12 You set the deletion flag in an order for the project, the system shows data from the order in the higher-level WBS element: Planned costs, if the order is appended
Q-13 The system determines the costs to complete (Cost Forecast) for Internal activity as follows: The planned start date is later than the key date in the
cost forecast
Q-14 The budgeting function helps you enter your budgeting data, but has limitations in the following areas : Availability control and distributed value check within
a project hierarchy
Q-15 For each project profile or order type, you specify in the budget profile in which currency the budget is to be entered ; Budgeting in the controlling area currency
Q-16 You set a global controlling area, and want to
monitor the budgets for all international subsidiaries.
Use the object currency for budgeting
|
|
Read Also
SAP PS Forum - Do you have a SAP PS Question? SAP Project System Books
SAP Project System Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|