What Is Overhead Cost And Overhead
Project
Costs, as you may very well be aware, are direct or indirect. The indirect costs - such as costs on welfare, subsidies, canteen, energy, transportations etc. are called over heads. Overheads are again classified into : (1) Production overheads (2) Commercial & Administrative overheads - This is dependent on where the incidence of cost occur. Overheads are generally calculated as a percentage of direct costs such as labour / material. Overhead projects - Projects are essentially of three
types in SAP-PS system -
Projects which are created to track and control overheads in an enterprise are called overhead projects. Example :- Travel expenses for a period. If you create a project such as this, it will enable tracking and controlling of travel expenses cost centre-wise, department-wise, employee-wise. To summarize: Overheads occur in every enterprise. But
some enterprises may choose to create a project to control certain specific
overheads. Such projects are called overhead projects.
My Client want to change the % Overhead rate periodically.
We are maintaining this in SPRO - Controlling.
We maintain overheads rate in costing sheet. Use transaction KZA1 Material Overhead system looks for material master --> Costing2 tab where we define material overhead key. In Config-> Product cost we assign a overhead key to a overhead group. In costing sheet row for material overhead - we maintain Overhead rate assigned to a Overhead key. We will see the actual OH - T.Code - KSI4 Please refer SAP Note 164222 - Transporting overhead rates of the costing sheet S_ALR_87008275 - Define Percentage Overhead Rate Once you change percentages, this will affect all the
transactions, like material cost estimate, actual overhead calculation
production order and if you use same cost sheet in other objects like networks,
wbs, internal order etc.
Which table can I see overhead rate which are created under costing sheet? In tables A... you find the "condition records" for different kind of overhead i.e. - A122 is for overhead according to profit centers - A014 according to overhead key - A013 is general and so on In table KONP you find rates for the "condition records"
found in A... tables
In which table overhead rate and percentage is maintained for transaction code KZZ2 ? The tables are: T685 - Conditions: Types KONX - Overhead Rates: Help Table for Variable Fields
Get help for your SAP PS problems
SAP Project System Books
SAP Project System Tips
Best regards,