CLOSING A PROJECT
-----Original Message-----
Hello, I tried to close a project # 2600000089. I am getting an error message " There is still WIP for WBS 2600000089 ". The long text suggests that " Calculate the WIP for WBS 2600000089 so that it can be cleared. Then settle WBS 2600000089, including the cleared WIP in the settlement ". I am not clear with this information. What should I do for this ?? We went from 3.1H to 3.1I about 20 days back. In 3.1H I have never come across like this.. Thank you .. -----Reply Message-----
Typically this occurs for one of two reasons:
-----Reply Message-----
Hi, You cannot close the project if you have a WIP value in it. It's because: 1. No invoice has been generated for that project. (fully invoiced status hasn't been reached). If you generate the invoice, the WIP value will be transferred to cost of sales. 2. Invoice has been generated but the WIP value is not yet settled fully due to some provision as provided by the difference between your plan values and actual values. Have both values equal and run the RA and settlement again. Once WIP is zero, then change the status to CLOSED. -----End of Message-----
Read Also
SAP Project System Books
SAP Project System Tips
Best regards,
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|