What are milestone?
Milestones are events that are of particular significance to the project flow. You can assign milestones to activities or WBS elements. If you want to use particular milestones several times in project planning, you should create standard milestones, and use these as templates to copy from. You use milestones in the Project System for the following tasks and functions: 1. To trigger defined milestone functions in activities 2. For the milestone technique of progress analysis 3. To determine dates in a sales order 4. For information purposes 5. For milestone trend analysis Milestone functions are functions in a network that are predefined by SAP. You can use them to trigger a sequence of steps that carry out a business process. e.g. 1. Release subsequent activities 2. Release up to stop indicator 3. Include standard network 4. Create network 5. Include subnetwork 6. Start workflow task
Problem Or Issues From Users What is the purpose of using "Release stop Indicator" and how does it work. How does trend analysis indicator work (related to dates in Milestone)? Answer Release up to Stop Indicator - It is like an activity milestone. It is used to release all subsequent activities. The automatic release process stops when it reaches activities that have been assigned a release stop indicator. Trend Analysis Indicator - This is used to analyze the
trend of the milestone dates based on planned and actual dates. It is used
for Milestone trend analysis done in CNMT tcode.
Milestone Function No Working I have created three network activities, I attached 1st milestone to the 1st activity using the function "release to stop indicator" and the system status which I chosen was 'REL'. Then second milestone to the third activity and marked it as stop indicator. When I am releasing the 1st activity, other activities are not getting released automatically. Answer In order to make this work you should set the milestone Function "release up to stop indicator" in the first activity. In the third activity, you should create another milestone and set the flag "stop indicator". Then you should link activities 1, 2 and 3 with relationships.
If the activities are not linked, the function to release up to stop indicator
will not be triggered.
Transaction Codes Transaction Function CN11 Standard Milestone: Create CN12 Standard Milestone: Change CN13 Standard Milestone: Display CNMT Milestone Trend Analysis CN13 Display Standard Milestones S_ALR_87015073 Individual Overview: Milestones
Self-Knowledge Evaluation Questions Milestone functions are functions in a network that a) Release subsequent activities
You create Milestone in PS: a) Mile stone can use in operative and standard WBS
|
|
Read Also
Get help for your SAP PS problems
SAP Project System Books
SAP Project System Tips
Main Index
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
|