Determine whether this statement is true or false.

1. Dynamic modification is possible at inspection lot creation or when making the usage decision.

True
False

2. If the action limits of a quality control chart are violated, the relevant inspection characteristic is rejected.

True
False

3. Quality control charts cannot be used for master inspection characteristics.

True
False

4. The quality score is updated when the usage decision is made.

True
False

5. The quality score has an effect on the vendor evaluation.

True
False

6. Activity confirmations for QM orders are only possible at results recording.

True
False

7. Evaluations are performed with reference to inspection lots or with reference to quality notifications.

True
False

8. The Early Warning System can be used to monitor critical key figures.

True
False

9. A movement of the data to external systems for evaluation purposes is not possible.

True
False

---

Explanation

1. Dynamic modification is possible at inspection lot creation or when making the usage decision.

Answer: True

Depending on the settings in the dynamic modification rule, dynamic modification takes place at either at inspection lot creation or in the usage decision.

2. If the action limits of a quality control chart are violated, the relevant inspection characteristic is rejected.

Answer: True

The quality control chart can be used to valuate the inspection characteristic and subsequently ensures the acceptance or rejection of the characteristic.

3. Quality control charts cannot be used for master inspection characteristics.

Answer: False

The SPC criteria define how the control chart is used. For example, a control chart can be created for the combination characteristic/material or for the master inspection characteristic.

4. The quality score is updated when the usage decision is made.

Answer: True

The procedure for the calculation of the quality score is defined in the inspection type in the material. The score is updated when the usage decision is made.

5. The quality score has an effect on the vendor evaluation.

Answer: True

In addition to the quality score, quality notifications can also have an effect on the vendor evaluation.

6. Activity confirmations for QM orders are only possible at results recording.

Answer: False

Activities can also be recorded in theQMorder when making the usage decision.

7. Evaluations are performed with reference to inspection lots or with reference to quality notifications.

Answer: True

This is true. Different InfoStructures are available for the standard analyses.

8. The Early Warning System can be used to monitor critical key figures.

Answer: True

Using the Early Warning System, the key figures on the InfoStructures can be monitored periodically.

9. A movement of the data to external systems for evaluation purposes is not possible.

Answer: False

The data can be moved to external statistical programs using the statistics interface QM-STI.
 

SAP QM

Also read
Action Box Configuration In Quality Notification

Have a SAP QM Problems?
SAP QM Forum - Do you have a SAP QM Question?

SAP QM Books
SAP Quality Management Certification, Interview Questions and Configuration Reference Books

SAP QM Tips
SAP QM Tips and Quality Management Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity. Information used on this site is at your own risk. 
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.