1) Which of the following can automatically
create a quality notification?
Note: There are 2 correct answers to this question. a. Confirmations for operations
from maintenance orders
Which is the correct answer? --- 2) Which QM master data must you maintain to plan a primary sample and a reserve sample? a. Sample-drawing procedure
Which is the correct answer? --- 3) Which entry is mandatory when recording a defect for the inspection lot? a. Confirmation profile
Which is the correct answer? --- 4) Which graphical nets are provided
in the Manage FMEAs app?
a. Graphical net for a structure
analysis
Which is the correct answer? --- 5) Which settings for sample determination
can you make in the inspection setup in the QM view of the material master?
a. Manual sample calculation
Which is the correct answer? --- Answers 1) b, c 2) a 3) c 4) a, b 5) a, b, e
|
|