The following are
simulated quality management questions for your self-evaluations.
1) During an audit you document a finding.
In the audit structure, what can link an audit and
a quality notification?
Please choose the correct answer.
a) Corrective/preventive action
b) Audit question
c) Business partner
d) Attached document
2) During quality inspection archiving, in which sequence
must the system process the data?
Please choose the correct answer.
a) Single Results, Characteristics and Operations, Samples,
Inspection Lots
b) Inspection Lots, Characteristics and Operations, Samples,
Single Results
c) Samples, Single Results, Characteristics and Operations,
Inspection Lots
d) Single Results, Samples, Characteristics and Operations,
Inspection Lots
3) What is the maximum number of function modules you
can assign to a single follow-up action for the usage decision in the Implementation
Guide (IMG)? Please choose the correct answer.
a) One
b) Zero
c) Ninety-nine
d) Unlimited
4) Which objects can you add as elements to the action
box of a notification type in the implementation guide (IMG)?
Note: There are 2 correct answers to this question.
a) Activities
b) Follow up actions
c) Documents
d) Tasks
5) Planned orders are scheduled in SNP with just one
PDS for a product.
How is the duration and end date of the order derived,
if you plan in weekly buckets?
Note: There are 2 correct answers to this question.
a) Results Recording
b) Control Charts
c) Usage Decision
d) Results History
e) O Defect Recording
6) What do you set up when implementing a DP scenario?
Please choose the correct answer.
a) Cost center
b) Control key
c) General ledger
d) Hourly wages
7) You want to record defects in inspection lot processing.
In the Implementation Guide (IMG), which elements
can you combine in a defect report type?
Please choose the correct answer.
a) Confirmation Profile, Catalog Profile, Notification
Type
b) Confirmation Profile, Defect Class, Origin of the
Catalog Profile
c) Confirmation Profile, Catalog Profile, Defect Type,
Work Center
d) Confirmation Profile, Catalog Profile, Origin of the
Catalog Profile
8) Which dynamic modification levels exist in the inspection
plan?
Note: There are 3 correct answers to this question.
a) Dynamic modification at character level
b) Dynamic modification at operation level
c) Dynamic modification at material level
d) Dynamic modification at inspection type level
e) Dynamic modification at lot level
9) You want to collect costs for repair work. What
must you define in the work center?
Please choose the correct answer.
a) Activity types
b) Formulas
c) Set-up time
d) Cost center
10. Which type of task list defines process steps independently
of the inspection lot?
Please choose the correct answer.
a) Routing
b) Inspection plan
c) Reference object set
d) Master recipe
---
Answers
1 a) Correct
1 b) Incorrect
1 c) Incorrect
1 d) Incorrect
2 a) Incorrect
2 b) Incorrect
2 c) Incorrect
2 d) Correct
3 a) Incorrect
3 b) Incorrect
3 c) Correct
3 d) Incorrect
4 a) Correct
4 b) Incorrect
4 c) Incorrect
4 d) Correct
5 a) Correct
5 b) Correct
5 c) Incorrect
5 e) Incorrect
5 d) Correct
6 a) Correct
6 b) Incorrect
6 c) Incorrect
6 d) Incorrect
7 a) Incorrect
7 b) Incorrect
7 c) Incorrect
7 d) Correct
8 a) Correct
8 b) Incorrect
8 c) Incorrect
8 d) Correct
9 a) Incorrect
9 b) Incorrect
9 c) Incorrect
9 d) Correct
10 a) Incorrect
10 b) Incorrect
10 c) Incorrect
10 d) Correct |