1. What Quality Management master data does an inspection with defect recording require?
Please choose the correct answer.

a) Task list
b) Catalogs
c) Inspection methods
d) Master inspection characteristics
 

2. When you create a task list for an inspection lot, which objects are available for inspection?
Note: There are 2 correct answers to this question?

a) Equipment
b) Batch
c) Handling unit
d) Material
 

3. When you activate QM in the material master in Procurement, to which organizational level does the function apply? Please choose the correct answer.

a) Controlling area
b) Client
c) Plant
d) Company code
 

4. On which structure level can you control Sales and Distribution processes within QM for material and customer data? Please choose the correct answer.

a) Company code
b) Sales organization
c) Distribution channel
d) Customer sales area
 

5. Your customer requires the receipt of incoming certificates.
Where do you allocate the certificate type when you activate Quality Management (QM) in Procurement?
Please choose the correct answer.

a) In the vendor master record
b) In the Q-info record
c) In the inspection plan
d) In the material master
 

6. Which of the following charts take into account only internal process parameters and not external tolerance specifications? Please choose the correct answer.

a) Shewhart Chart
b) Planning Control Chart
c) Acceptance Chart
d) Western Electric Chart
 

7. To which notification structure elements or objects can you assign catalog types?
Note: There are 3 correct answers to this question

a) Action
b) Documents
c) Partner
d) Task
e) Header
 

8. Which of the following controls a sample-managed process?
Please choose the correct answer.

a) Sample determination
b) Sample procedure
c) Sample plan
d) Sample draw
 

9. After you have approved all physical sample documents for a stability study, how do you close the corresponding inspection lots? Please choose the correct answer.

a) Remove the samples from storage.
b) Archive physical sample documents.
c) Change the test scheduling.
d) Make a usage decision.
 

10. When you perform calibration inspections, which objects do you combine with maintenance items in a maintenance plan? Please choose the correct answer.

a) Scheduling parameters and maintenance task lists
b) Scheduling parameters and maintenance orders
c) Scheduling parameters and inspection lots
d) Inspection characteristics and inspection plans

---

Suggested Answers

1 a) Incorrect 
1 b) Correct 
1 c) Incorrect 
1 d) Incorrect 

2 a) Correct
2 b) Incorrect
2 c) Incorrect
2 d) Correct

3 a) Incorrect
3 b) Correct
3 c) Incorrect
3 d) Incorrect

4 a) Incorrect
4 b) Correct
4 c) Incorrect
4 d) Incorrect

5 a) Incorrect
5 b) Incorrect
5 c) Incorrect
5 d) Correct

6 a) Correct 
6 b) Incorrect 
6 c) Incorrect 
6 d) Incorrect 

7 a) Correct
7 b) Incorrect
7 c) Incorrect
7 d) Correct
7 e) Correct

8 a) Incorrect
8 b) Correct
8 c) Incorrect
8 d) Incorrect

9 a) Incorrect
9 b) Incorrect
9 c) Incorrect
9 d) Correct

10 a) Correct
10 b) Incorrect
10 c) Incorrect
10 d) Incorrect

SAP QM Tips

Also read

Have a SAP QM Problems?
SAP QM Forum - Do you have a SAP QM Question?

SAP QM Books
SAP Quality Management Certification, Interview Questions and Configuration Reference Books

SAP QM Tips
SAP QM Tips and Quality Management Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity. Information used on this site is at your own risk. 
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.